Legal Issues Converting Condos And Apartments To Hotels

Category: Hotels, Posted:29 Aug 2011 | 06:00 am

As Phuket property continues to face broad challenges the issue of conversion of buildings into hotels is increasingly being looked at by developers.
We asked Jerrold Kippen at the Phuket law firm of Duensing Kippen in Phuket to clarify the legal ramifications of the issue. It's an interesting subject with details as follows:
"The Building Control Act (1979) ("BCA") generally regulates the construction and use of buildings in Thailand. Unless the BCA states otherwise, any construction of any building must be permitted by the relevant Local Administrative Office (e.g. Tetsabaan or Or Bor Tor, etc, depending on where you are located in Thailand) that oversees such matters in the area in which the building is located. In order to obtain the building permit, the applicant must, among other things, state the purpose for which the building is intended to be used. Such intended use will then be stated on a building permit; for example, "residence" for any residential villa, "hotel" for any hotel and "condominium" for any condominium, etc.
What if the owner of, say an office or apartment building, decided he could have a much more lucrative asset by changing it into a condominium and sell the units or into an hotel and run it as such? Is that "doable" in Thailand? The answer is a qualified "yes".
Pursuant to Section 32 of the BCA and the 2009 Ministerial Regulation issued thereunder, any "hotel; condominium; warehouse; hospital; hazardous goods storage room; dormitory or common residential building (e.g. an apartment) that is a "Large Building "; convention hall or office building having a total floor area of 300 square meters or more; any building used for any commercial purpose and having a total floor area of 300 square meters or more; or any building used for any industrial or educational purpose" is a building subject to control over its use (a "Use Controlled Building").
Section 32 of the BCA further prescribes that on completion of the construction of the Use Controlled Building a notification must be given to the Local Administrative Office to inspect the structure. After the inspection, if the Local Administrative Office determines that the construction was completed in accord with its building permit, permission to use the building will be granted. A Certificate of Use for the purpose applied for in the building permit will be issued. If, however, the Local Administrative Office does not inspect the building within 30 days of the notification of completion, the owner or possessor of the building may go ahead and use or allow others to use the building for the purpose stated in the building permit.
In addition, Section 33 of the BCA provides that the owner or possessor of the non-Use Controlled Building must not use or allow others to use it for any purpose specifically reserved for Use Controlled Buildings. Neither may a Use Controlled Building be used for any purpose reserved for Use Controlled Buildings other than the purpose for which it was originally permitted. However, the exception to this rule is if a permission for such is granted by the Local Administrative Office.
Thus, to change any non-Use Controlled Building to a Use Controlled Building or one type of Use Controlled Building to another type of Use Controlled Building (regardless of whether or not the building is yet to be constructed, under construction or is already completely built) the following steps must be followed:
1. Pursuant to 1985 Ministerial Regulation No. 10 issued under the BCA, the following documents must be submitted to the relevant Local Administrative Office:
(a) A copy of any document that legally evidencing who owns or possesses the building;
(b) A consent letter from the owner of the building (if the applicant is not the owner, but is the possessor of the building);
(c) A permit to change a purpose of use of the building (if the change of purpose of use of the building was permitted before);
(d) A signed copy of the applicant's corporate documents at least 6 months update and the authorized director's identification card and house registration or passport (if the applicant is a company);
(e) 5 copies of the building plan;
(f) A calculation report on the building's structure (if the change of purpose of use of the building will decrease the weight-carrying capacity of the building);
(g) A letter of approval and certification of the calculating engineer and a copy of the Thai engineering license of said engineer (if, pursuant to the BCA, the building requires engineering control); and
(h) Any other supporting documents required by the Local Administrative Office.
2. Pursuant to the BCA, the Local Administrative Office must then either issue a permit to change the purpose of use of the building (a form of which is called "OR. 5") or deny the issuance thereof and inform the applicant in writing with the reasons for the non-issuance, within 45 days from the date of the application. However, also under the BCA, the local administrative office may extend the deadline for up to two additional 45 day periods for any reasonable cause; if so, the Local Administrative Office is required to notify the applicant in writing of the cause for the extension(s).
It should be noted that any change of purpose of use of a building to a non-controlled use, does not require governmental permission.
In closing, it should also be noted that getting a building permitted and certified for use as a condominium or hotel is not the "end of the regulatory road". There are other legal requirements conditioned on and subsequent to obtaining the correct building permit and use certification before the building can be operated as a condominium or hotel, such as obtaining the requisite condominium or hotel license."

Other News

Read more

MIRA Valley Phuket Preview Sessions This Friday

Category: Real estate|Tourism, Posted:22 Apr 2024 | 07:28 am Catch this special event this coming Friday 26th April with a special preview of the new MIRA Valley master-planned community in the heart of Phuket, Manik. This is an amazing opportunity to acquire a development plot in a larger high-quality community. This will be of special interest to property developers looking for land parcels, investors. […]
Read more

New Phuket Hotel Market Update 2024 Report From C9 Hotelworks

Category: Hotels|Tourism, Posted:17 Apr 2024 | 19:06 pm Phuket’s tourism industry is undergoing an ongoing rebound, with last year’s airport passenger arrivals edging towards pre-pandemic figures according to C9 Hotelwork’s Phuket Hotel Market Update 2024. While hitting 7 million, it was still short of the 9 million mark set in 2019. This year the trend is continuing with 1.62 million arrivals to date […]
Read more

Delving Into the Real Estate Rental Landscape of Phuket

Category: Opinion|Real estate, Posted:16 Apr 2024 | 09:39 am Given the backdrop of a booming Phuket real estate sector, one area that is often overlooked is the rental market. Despite a vibrant vacation short-stay segment, there remains a strong demand for extended and long-stay rentals across the island. Rental demand coming out of the COVID19 pandemic experienced sustained uplift and has continued to perform […]
SiaJai logo

Thailand's Leading Homecare Marketplace